View All News
April 9, 2020
By joey

Stem Walls, Temporary Offices

Construction on the Expansion Project continues as the Library Agency on April 6 determined that the Expansion is an exempt public works project under the latest County Health Order.

Now that the concrete slab on grade has been poured, current work is centered upon the forming of the stem walls that will support the floor of the expanded Library. The schedule forecasts that these walls will be poured on April 14.